Erecting steel frames in factory construction involves many important stages. Each stage includes strict procedures to ensure the best quality and safety for customers. In the article below, Hai Long will provide a detailed introduction to the erection process of pre-engineered steel buildings as well as the principles that must be followed during erection.
Erection is the final step in the pre-engineered steel building construction process. In this step, all components, steel frames, and materials are transported from the manufacturing plant to the construction site for assembly.
1. Erection process for pre-engineered steel buildings
To ensure the safety and quality of the project, the erection process for pre-engineered steel buildings is carried out in the following sequence:

Step 1: Planning and site preparation
- Site survey: Check that the construction access roads are sturdy enough for transport trucks and cranes to operate.
- Check the material staging areas, ensuring that materials are stored in designated areas for the most convenient construction access.
- Based on site conditions, develop a construction plan and notify the factory so that it can plan production and supply accordingly. It is necessary to ensure that the supply schedule is synchronized and does not affect the progress of other departments.
- Inspect and survey electrical connection points before construction. Ensure that power sources are routed to the construction area in the safest manner.
- Organize occupational safety training for workers.
- Inspect construction equipment, tools, and machinery to ensure all equipment meets normal operating requirements.
Step 2: Surveying anchor bolt positions
- Before installing the steel structure, re-survey the positions and elevations of the pre-installed anchor bolts (this is known as the anchor bolt positioning as-built step).
- Positioning markers and elevations must be based on the required design elevations.
- All surveying equipment must be accurately calibrated.
- Anchor bolts must be secured against horizontal, longitudinal, and vertical displacement throughout the entire process from installation until after concrete pouring.
- Permissible tolerances are as shown in the following table:
| Position deviation | Permissible tolerance |
|---|---|
| Center-to-center distance deviation between 2 bolts in a cluster | ≤ 5mm |
| Center-to-center distance deviation between 2 adjacent bolt clusters | ≤ 10mm |
| Elevation deviation between anchor bolt tops | ≤ 15mm |
Step 3: Material delivery and receipt at the construction site
- A key characteristic of pre-engineered steel buildings is that all components are prefabricated at the factory. During construction, any deviation or missing component will directly affect the erection progress on site.
- Delivery notes are required, and both the receiving and delivering parties must sign for confirmation. During the material receipt process, each item must be cross-checked against the delivery note, and the received quantity must be confirmed on the note. Additionally, a preliminary quality assessment of the materials must be conducted before deciding whether to accept them. Ensure all materials and components are present to guarantee the continuity of the erection process.
Step 4: Material storage at the construction site
- Select a solid, compacted, and dry area as a temporary warehouse for auxiliary materials.
- Materials should be stacked at locations corresponding to the specific part of the structure or area to be built, preferably near the position where the crane will operate for installation. This will facilitate convenient sorting and delivery throughout the construction process.
- Materials must be protected from dust, grease, and other impurities; they must also be shielded from water contamination caused by construction vehicles on site.
- Do not walk or step on materials and components.
- All bolts, nuts, screws, small gusset plates, and accessories must be properly packed and labeled.
Step 5: On-site erection
- Depending on the nature of the project, construction may be carried out using different methods, based on several key factors as follows:
– Type of structure (e.g., small-span buildings, large-span buildings, low-rise buildings, high-rise buildings, I-beam structures, open-web structures, etc.)
– Type of available equipment (e.g., cranes, forklifts, winches, manual hoists, etc.)
– Existing site conditions
– Experience of each erection team
- The construction sequence/method must be studied and planned to ensure that work can be carried out safely, economically, and efficiently.
- Specific construction procedures for each project must be discussed in advance, detailing all requirements before implementation. Different construction methods will be applied based on the specific characteristics of each project.

Step 6: Supervision plan and Acceptance inspection
a. Acceptance inspection
The acceptance inspection for steel structure erection is conducted in the following steps:
- Inspection of each item before proceeding to the next stage (internal acceptance)
- Inspection and acceptance of completed items (conducted by the construction supervision consultant)
- Final acceptance and handover of the project (with all participating parties present)
b. Supervision and inspection plan
Bracing bay inspection
- After installing the first two frame rafters of the rigid bracing bay, the site supervisor will pause work and notify the Project Manager to inspect and sign off on the internal inspection step before the Client's supervisor conducts their inspection.
- The Project Manager must inspect and sign off on the status of the bracing, recording it to ensure the structure does not shift incorrectly or collapse during the installation process.
Bolt tightening force inspection
- 100% of structural bolts must be checked by the team leader for tightening force to ensure compliance with requirements and must be marked. The inspection tool used is a calibrated torque wrench.
- The bolt tightening process, including the final tensioning, must proceed from the stiffest part of the connection toward the edges. Avoid re-tightening bolts that have already been fully tensioned:
– As an exception, when re-tightening is necessary, it is only permitted once, provided the bolt remains in the same hole (where it was previously tensioned) and the same wrench length or tightening tool is used.
– Re-tightening of galvanized bolts is not permitted.
– Under no circumstances is it permitted to reuse bolts that have already been fully tensioned.
– Tightening or re-tensioning bolts that have loosened during the tightening of adjacent bolts is not considered re-tightening. The final bolt tensioning shall only be performed after the alignment and elevation satisfy the requirements.
- Bolt tightening sequence:

The figures above illustrate the permitted tightening sequence for any connection.
- The tightening process is carried out in two rounds; the second round ensures all bolts are tightened to a uniform torque. Use the permitted torque for tightening and inspection. In completed connections, all bolts must reach the minimum required tension.
- Alternative bolt tension inspection method: Use a torque wrench with a range corresponding to the permitted tightening torque of the bolt.
Alignment Inspection
- Verify and provide a formal report on the alignment of one main frame and two gable frames. If feasible, alignment should be adjusted immediately after the installation of each frame section. Do not perform permanent connections until a suitable portion of the frame system has been aligned for position, elevation, and verticality, and temporarily braced to ensure the components do not shift during the installation and alignment of the remaining frame system.
Acceptance
- Internal acceptance must be performed first. This inspection aims to ensure quality requirements are met and to plan for adjustments, cleaning, and touch-up painting.
- Applicable Standards:
– TCXD 170-2007: Steel structures – Fabrication – Erection – Acceptance – Technical requirements
– TCVN 5593: 2012 Construction work for buildings
2. Construction Equipment
a. Mobile machinery
- Mobile machinery includes delivery trucks, boom trucks, hoists, etc.
- Only mobile machinery that has been inspected and operated by skilled personnel is permitted on the construction site.
- In areas where there is a risk of mobile machinery coming into contact with electricity, all power lines must be fenced off or marked with warning flags. Power lines posing a risk of accidents must be de-energized or made safe before commencing any work.
- No machinery is allowed to operate directly over power lines.
- Never operate machinery within 4.5m of a power source exceeding 220 Volts.
- Avoid walking near or directly under an object being lifted. All heavy objects being lifted must have taglines for guidance.
- Before lifting anything, clearly define the crane's position and the landing area within the construction site. Conduct occupational safety measures and analyze potential risks (based on the On-site Installation Safety Procedure).
- During all stages of construction, avoid or minimize damage to the finish paint of the structure by using nylon slings or belts with protective padding at points of direct contact with steel components, or by using shackles through bolt holes for lifting.
b. Lifting slings and rigging
- Thorough inspection of lifting cables and rigging is mandatory. Damaged cables and slings must be cut and discarded immediately.
- When lifting, avoid improper use of slings. Protect slings by padding sharp corners. Absolutely no sudden jerking during lifting, as this can increase the load by three times the normal amount, endangering the slings. When not in use, store slings neatly. Never overload a sling.
c. Construction Scaffolding
- Plan the use and installation of scaffolding so that it does not obstruct the movement of cranes or their boom reach, nor hinder construction operations.
- Always place scaffolding on firm ground or use base plates with a minimum size of 200 x 200 mm. Individual scaffolding units must be securely tied to a fixed structure with a minimum gap of 1.5m. Each upper level of scaffolding must be secured to the lower level with steel wire or scaffolding pipes to ensure safety.
d. Hand tools
- All hand tools must have lanyards to prevent them from falling during work.
- Use equipment for its intended purpose. Never use hand tools for tasks outside their intended scope. Never use temporary makeshift equipment.
- Never use damaged tools, or machinery with frayed cords, defects, or missing safety guards.
3. Steel structure erection method for a typical steel building frame
[STEP 1] ERECTING THE BRACED BAY COLUMNS
a. Installing the first column
- The first column must have anchor cables to secure it after installation.
- Cable anchor points can be piles or anchor bolt clusters nearby.

b. Alignment of verticality, position, and elevation
- Move the man lift to the column position.
- Tighten the anchor bolts moderately, and align the column base as required.
- Equipment: Plumb line, theodolite, and tape measure.
- Tighten all anchor bolts with a wrench to the specified torque.
c. Install the next column and column bracing or wall girts between columns
- Bracing/girts must be installed immediately to ensure column stability.
- Bolt tightening force should be sufficient to maintain stability.

[STEP 2] INSTALLATION OF THE FIRST RAFTER BEAM
a. Assembly of rafter segments on the ground
- Rafter segments are assembled on the ground according to the installation diagram.
- Cables are attached to the component at two points approximately 1/4 of the length from the ends, next to the girt cleat/stiffener. However, the section beyond the lifting point must be calculated to avoid twisting the component due to its own weight. The section beyond the lifting point must not exceed 1/3 of the component length. The lifting angle must also be calculated to avoid twisting due to longitudinal forces during lifting. For safety, it is recommended to use more than two lifting cable attachment points.
- When assembling, use 50mm thick wooden blocks to support the components.
- High-strength bolt tightening equipment: Torque wrench, tightening force according to the minimum recommended torque (see Torque Table).
- Install temporary bracing and girt struts to the rafters.
- Use sandpaper and a cloth to clean the components. Touch up scratched paint with a paint roller.
- Perform 1 to 2 test lifts to check the balance of the lifting cables.
b. Install one rafter half onto the columns
- Lift the first rafter half and place it onto the heads of two consecutive columns, keeping it stable with the crane.
- Workers will operate from a man lift or a safety cage, inserting and tightening the flange bolts connecting the column and rafter beam until sufficiently tight.
- Use temporary cable bracing for the rafter beam, placed approximately 6m apart, to secure this first rafter half to the column base bolt clusters using V-shaped steel brackets.
- Slightly release the lifting cable to check if the rafter half is stable before fully releasing it.

c. Repeat steps 1 and 2 for the remaining rafter half to form a complete rafter frame
[STEP 3] INSTALLATION OF THE SECOND RAFTER FRAME
a. Perform the same procedure as step 2 for the two rafter halves of the second rafter frame
- Only use temporary bracing on both sides at the middle of each rafter half, secured to the column base bolts using V-shaped steel brackets.
b. Immediately install ridge bracing/temporary girts to keep the rafter halves in the correct position

[STEP 4] COMPLETE 100% OF THE BRACED BAY
- Install all rafter bracing, girts, and girt struts – 100% of the required quantity.
- Install all permanent cross-bracing cables for columns and rafter beams for the braced bay.
- Leave these braces in a loose state (not yet tensioned).
- Align the rafter frame:
– Use temporary braces to align the frame.
– Fully tighten the permanent braces.
– Sign the inspection report for the completed braced bay.

[STEP 5] INSTALLATION OF ALL REMAINING RAFTER FRAMES AND PURLINS
- Install all side columns and interior columns at the subsequent axes.
- Adjust the verticality, position, and elevation of the columns.
- Perform the same procedure as [step 3] and [step 4] for all rafter frames and roof purlins.
- For structures with a center column, it is not permitted to install one side of the rafter half before the other. Doing so will alter the design calculation scheme of the frame, causing frame imbalance, which may lead to structural collapse during adverse weather conditions.
[ STEP 6 ] INSTALLING THE END GABLE RAFTER
- Complete the installation of the end gable rafter frame following the same sequence as the previous steps.
- Install 100% of the rafter bracing, purlins, purlin struts, and purlin sag rods for the remaining two end gable bays.
- Install all permanent cross-bracing for columns and rafter beams for the final braced bay.
- Leave these braces in a loose state (not yet tensioned).
- Align rafter beams
- Fully tighten all permanent bracing.
- Remove all temporary bracing from the structure.
- Inspect and verify all connections, ensuring all bolts are installed. All high-strength bolts (structural bolts) must be tightened to the required torque. Bolts must be marked after reaching the required torque to ensure none are missed.
- Perform a final inspection of the entire steel structure: verify correct layout orientation and verticality.
- Prepare the acceptance report.
[ STEP 7 ] ROOF SHEETING INSTALLATION
- Lift roof sheets to the roof using a sheet lifting cradle
- Use guide ropes for positioning
- Lift sheets in bundles bay by bay, placing them close to the steel rafter frame
- Sheet stacks must be securely tied with 3mm steel wire at a minimum of 3 points and have measures to prevent sliding.
- Once sufficient sheets are lifted, the installation team will begin the roofing work.

[ STEP 8 ] SHEETING INSTALLATION
- Install safety cable system on the roof
- Prepare the construction power system
- Install the first roof sheet:
– Position the first sheet, ensuring the overhang into the gutter is even and between 100-150mm.
– Drive positioning screws for the first sheet.
- Join the next sheet so that the ribs interlock perfectly with the first one
- Regularly check that the installed sheets are aligned straight along the gutter edge.
- Drive 100% of the screws according to the sheet type.
- Apply silicone sealant to 100% of the screw heads
- Regularly use a brush to clean off metal filings and dust
- If the roof uses insulation material, this material must be laid out first before placing the roof sheets on top. The insulation must be laid taut and flat to ensure aesthetics and quality.

[ STEP 9 ] INSTALLING WALL SHEETING – GUTTERS – DOWNSPOUTS AND ACCESSORIES
- Prepare access ladders
- Use pulleys and ropes to pull each sheet into the installation position
- Workers drive positioning screws while standing on access ladders
- The first sheet must be plumbed vertically before driving screws.
- Subsequent sheets must be checked and aligned regularly to prevent sheet drift.
- Sheets must be cleaned before installation
- Install gutters, downspouts, flashing accessories, etc.