On May 27, 2022, the expansion of Yen My II Industrial Park was officially approved for investment policy by the Government under Decision No. 650/QD-TTg, with the investor for the construction and infrastructure business project of Yen My II Industrial Park being Hoa Phat Hung Yen Industrial Park Infrastructure Development Co., Ltd.
Overview Information
- Name: Yen My II Industrial Park – Hung Yen
- Scale: 313.5 ha
- Occupancy rate: 31%
- Investor: Hoa Phat Hung Yen Industrial Park Infrastructure Development Co., Ltd.
- Infrastructure usage fee: 130 USD/m2. Price excludes VAT
- Industries attracting investment: environmentally friendly investment sectors such as electronics assembly, automotive and motorcycle mechanics, steel production, steel products, pharmaceuticals, etc.
Geographical Location
Yen My II Industrial Park has a favorable location, adjacent to National Highway 39, which is a route connecting two important traffic axes: the Hanoi – Hai Phong Expressway and National Highway 5, and:
+ 30 km from the center of Hanoi city
+ 50 km from Noi Bai International Airport
+ 75 km from Hai Phong Port
In addition, the easy traffic connection makes it extremely convenient to travel from Yen My II Industrial Park to important economic centers such as Bac Ninh, Hai Duong, Hai Phong, Bac Giang, and Ha Nam.

Infrastructure system at Yen My II Industrial Park – Hung Yen
- Power supply system: Production power in Yen My II Industrial Park is guaranteed to be supplied by a 110kV/22kV substation with a capacity of 63 MVA, supplied from the national power grid.
- Water supply system: Yen My II Industrial Park has invested in building an internal water supply system with a designed capacity of 7,500 m3/day and night. At the same time, water supply pipelines are pre-connected to each land plot in the industrial park.
- Wastewater treatment system: The internal wastewater treatment system has a maximum treatment capacity of 6,000 m3/day and night, capable of treating wastewater from column B to column A according to Vietnam's environmental technical standards.
- Internal traffic system: The main roads in Yen My II Industrial Park are designed with a width of 50 m, and branch roads have a width of 23.5 m.
- Fire protection system: Firefighting water systems and fire hydrants are arranged along the traffic routes in the industrial park to ensure quick response to fire incidents within the industrial park.
- Communication system: The telecommunications and communication system is guaranteed to be ready and connected according to the needs of investors operating in the industrial park.
- Other utilities: Besides technical infrastructure works, Yen My II Industrial Park reserves 13% of the planned area to build landscape and green infrastructure to maintain environmental friendliness and an airy space for the industrial park.
Current status of investment attraction
Currently, for the existing area of 97.5 ha, the entire area has been leased and filled to 100% with typical projects such as: The beverage factory of Tribeco Northern Co., Ltd.; The glass door manufacturing factory of Austdoor Hung Yen One Member Co., Ltd., the pharmaceutical production project of Napharco Pharmaceutical Co., Ltd... and a series of projects by domestic and foreign investors.
For the expanded planned area, the investor is currently urgently implementing compensation and site clearance work and expects to deploy infrastructure construction from the end of 2022.
Investment Costs
Incentives when investing in Yen My II Industrial Park – Hung Yen
– Exemption from import tax on goods to create fixed assets
– Corporate income tax: Exemption from tax for 02 years and a 50% reduction in tax payable for the next 04 years for new investment projects in the industrial park.