On the HHD Thai Ha project site, the construction atmosphere is always vibrant and urgent. Each item marks significant progress, reflecting the sense of responsibility, professionalism, and determination of the entire team at the general contractor, Hai Long Construction.
- The factory building has completed its 3-story reinforced concrete rigid frame. Finishing masonry and plastering work have reached 60% completion, giving this key area an increasingly clear appearance.
- The warehouse has also recorded impressive construction speed, having completed the reinforced concrete foundation, as well as the installation of the steel structure, roof sheeting, and wall cladding.
- The firefighting water tank and wastewater treatment tank have both reached 100% completion, meeting all safety and environmental standards.
- Auxiliary items such as the waste storage building and chemical warehouse have completed their rigid frames, enclosures, and roof sheeting, while guardhouses 1 and 2 are also finished and ready for use.
- The parking garage has completed its foundation and is currently implementing the base layer, promising to be finished soon to serve the needs of staff and employees.
- In particular, the MEP system (mechanical, electrical, plumbing, firefighting, etc.) is being implemented synchronously with the construction items, ensuring connectivity and optimized operation for the entire project.
Looking back at the images from the HHD Thai Ha site, the efforts and smooth coordination of the Hai Long Construction team and related parties are clearly visible. This is not only a testament to the project organization and management capacity but also a strong commitment to quality, schedule, and safety by the general contractor.
Some images from the project site