At the major construction site of the Fanstech Vietnam Factory, Hai Long Construction, acting as the General Contractor, is maintaining a focused construction pace, applying effective project management measures to ensure safety, quality, and strictly adhering to the key milestones committed to the Investor.
The current construction focus is on the two main factory buildings.
- For Factory X1, Hai Long Construction has completed 100% of the rigid frame (reinforced concrete structure). In particular, the entire volume of floor beams at the 10.4m level – one of the complex components requiring high construction technique due to the very large floor height – has been completed. Construction teams are urgently implementing subsequent tasks, with steel structure erection reaching 50% and wall construction reaching 30% of the volume.
- In parallel, Factory X2 has also completed 100% of the rigid frame. The progress of finishing items is following X1 closely, with steel structure erection reaching 50% and wall construction reaching 35% of the volume.
- To ensure the overall handover goal, other infrastructure and auxiliary items (such as internal roads, drainage systems, guard houses, etc.) are also being implemented synchronously, ensuring no impact on the overall progress of the entire project.
With the current progress, the Project Management Board is well controlling the items and confirms the commitment to hand over the Level 01 area (Factory X1) for the Investor to install machinery and equipment in October 2025. Subsequently, the Level 02 area (Factory X2) will be handed over in November 2025, and the overall project will be handed over in January 2026.
With the capacity and experience of a professional General Contractor, Hai Long Construction continues to affirm its strong commitment to bringing the Fanstech Vietnam project to the finish line on time, safely, and with the highest quality.