With a strategic vision and a suitable business plan, along with the trust of the Investor, TSMT Vietnam Co., Ltd., Hai Long Construction has successfully won the construction bid for the TSMT Vietnam Factory Project.
Project Information:
– Investor: TSMT Vietnam Co., Ltd.
– General Contractor: Hai Long Construction JSC.
– Project Address: Land Lot CN01, Thai Ha Industrial Park, Bac Ly Commune, Chan Ly Commune, Ly Nhan District, Ha Nam Province.
– Contract Value: Nearly 200 billion VND.
– Construction Area: 17,480m2
– Production workshop and office construction area: 13,500m2
– Expected Completion: December 15, 2023.

The Investor, TSMT Vietnam Co., Ltd., specializes in providing surface-mount technology (SMT) manufacturing solutions for liquid crystal display (LCD) screens in Taiwan and internationally. The TSMT Vietnam Factory project is invested with the goal of manufacturing and processing PCBA for HDMI display systems and Trinity Cameras.
Through the process of researching and studying the market in Vietnam, the Investor has chosen Hai Long Construction JSC as the general contractor for the project. With experience accumulated from previous large-scale projects, Hai Long Construction has demonstrated professionalism and reliability, earning the full trust of the Investor.

On May 11, 2023, the Groundbreaking Ceremony of the TSMT Vietnam Factory Project was held at Thai Ha Industrial Park, Bac Ly Commune, Chan Ly Commune, Ly Nhan District, Ha Nam Province. The ceremony was attended by partners, customers, and the Board of Directors of Hai Long Construction, including:
– Representative of the Investor: Mr. Wu, Yun Chung.
On behalf of Hai Long Construction JSC, attendees included:
– Mr. Pham Tien Dung – General Director of the Company.
– Mr. Pham Trung Lanh – Deputy General Director of the Company, along with the Deputy Director of the Project Board and the project management team of TSMT Vietnam.
On behalf of Thai Ha Industrial Park, attendees included Mr. Ngo Van Hai – General Director and Ms. Le Minh Tu – Sales Director from Thai Ha Industrial Park & Urban Investment JSC.
The honorable guests at the Groundbreaking Ceremony and the Board of Directors of Hai Long Construction JSC delivered speeches and conducted the Groundbreaking Sand-shoveling Ceremony to pray for luck, peace, and the success of the project.


The TSMT Vietnam Factory project is the next major project being implemented by Hai Long Construction in Ha Nam province, alongside ongoing projects such as the GNP Dong Van Industrial Center and the Chi Chau Printed Circuit Board Company project (also known as the TPT Ha Nam project). This is not only a testament to the capabilities of Hai Long Construction but also a reflection of our daily efforts to provide peace of mind and satisfaction to our valued customers.

Finally, we sincerely thank the representatives of the Investor, TSMT Vietnam Co., Ltd., and the representatives of Thai Ha Industrial Park for attending and ensuring the success of the ceremony, promising another multi-million dollar project to be conquered by Hai Long Construction JSC.