At the Viet Phap Steel Sheet Factory project site, the urgent pace of the team of Hai Long Construction engineers and workers is pouring all their heart and intellect, day and night, into creating a modern, solid industrial facility.
– The main factory building has completed the steel structure erection. Currently, the roof and wall cladding have reached 60% of the volume, and the remainder is being urgently executed in parallel with the completion of the machine foundation system, ensuring synchronization and optimization of the schedule.
– Key machine foundation items have also recorded positive results:
- Rolling machine foundation: 100% of the work volume has been officially completed.
- Descaling machine foundation: Urgently heading to the finish line with 90% of the work volume completed.
– In addition, other important auxiliary works are also being implemented synchronously and effectively.
The smooth coordination between construction teams, along with the professional project management of Hai Long Construction, has been helping the items of the Viet Phap Steel Sheet Factory project to be implemented synchronously, effectively, and safely, confidently bringing the project to the finish line this coming July 2025.