UBND tỉnh Bắc Ninh vừa ban hành Quyết định số 330/QĐ-UBND phê duyệt đồ án điều chỉnh Quy hoạch phân khu Khu công nghiệp (KCN) Quế Võ mở rộng 2, tỷ lệ 1/2.000.
Accordingly, the MN02 drainage canal route has been adjusted to shift to the West, bordering the western boundary of the industrial park and adjacent to the residential area of Yen Gia village (Chi Lang commune). The adjustment helps ensure drainage for the entire area while increasing drainage capacity for the existing residential area. The drainage direction, connection points, and technical solutions remain unchanged compared to the previously approved general plan, ensuring consistency in technical infrastructure.
Notably, Bac Ninh province also decided to merge land plots B and C into plot BC with an area of approximately 32.6 hectares; and merge land plots E and F into plot EF covering 22.85 hectares. This merger aims to create large-scale land funds suitable for arranging production lines, factory buildings, and auxiliary items according to the actual needs of investors. The above adjustments are only local and do not change the land use structure or the overall scale of the project.

Previously, in August 2025, the People's Committee of Bac Ninh province approved the 1/2,000 scale zoning plan for the Que Vo 2 Industrial Park expansion, invested by Kinh Bac City Development Holding Corporation (KBC). The industrial park has a total area of over 140.3 hectares, located in Bong Lai ward, Phuong Lieu ward, and Chi Lang commune. In which, about 91 hectares are planned for the construction of factories and workshops; more than 13 hectares are reserved for administrative and service items; the remaining area is allocated for greenery, internal traffic, and water surfaces.
According to the plan, the industrial park is divided into seven large plots with a maximum construction density of 70%, and industrial building heights not exceeding 7 floors. The service area is allowed to be built up to 18 floors high with a density of 50%. The parking lot is located in the South, adjacent to DT.287 road, serving the logistics and travel needs of workers.
Kinh Bac expects to start construction of the project in the first quarter of 2026, complete it in the fourth quarter of 2029, and can begin operations from the second quarter of 2028. The total investment is about 1,878 billion VND, of which construction costs account for more than 1,176 billion VND, and compensation and site clearance costs are about 702 billion VND.
Currently, Kinh Bac has invested in three industrial parks in Bac Ninh, including Que Vo, Que Vo expansion, and Nam Son – Hap Linh. The implementation of the additional Que Vo 2 Industrial Park marks the company's fourth industrial project in the locality, while consolidating Kinh Bac's position in the field of industrial infrastructure development.
According to the investor's orientation, Que Vo 2 expansion will become a multi-industry, high-tech industrial park, focusing on attracting enterprises in the fields of electronics, electronic components, precision mechanics, and supporting industries. The project is expected to continue the success of the two previous Que Vo industrial parks – which have filled 100% of commercial land with a total attracted investment of over 3 billion USD since starting operations in 2003.
With reasonable planning adjustments, synchronous infrastructure, and a focus on attracting high-tech investment, Bac Ninh continues to affirm its role as one of the leading industrial centers in the North, contributing significantly to the development strategy of the Capital region and the Northern key economic region.
Source: Nguoi Quan Sat Electronic Newspaper