With the trust from the Investor, the contractor Hai Long Construction continues to execute the Primzen Electronics Phase 2 project, which has been implemented since March 2023 and is being constructed within 90 days.

After completing Phase 1 as committed, Hai Long Construction has once again received the trust of the Investor and is gradually completing the Primzen Electronics Phase 2 project. The Primzen project is updated as follows:
- Currently, the 4th floor of the project has been completed, and the installation of the fire protection system, as well as electrical and water systems, is being rushed.
- External infrastructure is being constructed, including internal roads and green landscape areas.


The Primzen project is built at Trang Due Industrial Park and is one of the projects that Hai Long Construction has dedicated much effort and commitment to completing on schedule, ensuring quality, and always focusing on security and safety at the project site.