With the persistent fighting spirit of the Board of Directors and the staff at the Jinka Phase 3 project, the project update is as follows:
- Factory X3 is currently installing the steel structure and roof purlins.
- Factory X4 has completed approximately 70% of the second-floor columns and is preparing to install the roof steel structure.
- Factory X5 has completed approximately 90% of the second-floor columns and is preparing the site for steel structure installation.
- Factory X6 has finished installing the roof steel structure and roof purlins.
- Factory X7 has completed the roof cladding structure.



Hai Long Construction always strives and makes every effort, regardless of the harsh summer heat, to focus on the project carefully and meticulously, ensuring security, safety, and high quality to hand over according to the schedule committed to the Investor.