After a relatively stable period in 2025 and the first two months of 2026, construction material prices rose sharply from March due to fluctuations in gasoline and oil prices, especially diesel, amid the conflict in the Middle East. Cost pressures and fuel supply issues have affected many key projects, forcing the Ministry of Construction to introduce market stabilization solutions.
Cement, steel, sand, and stone prices rise simultaneously
According to the Ministry of Construction, as of March 31, 2026, cement prices increased by over 7%, steel by over 2%, floor tiles by nearly 5%; materials such as sand, stone, and construction bricks increased from 13.5% to 23.3%, while asphalt alone increased by nearly 32%. Recorded in Hanoi, construction stone prices rose from about 350,000 VND/m³ to about 670,000 VND/m³, construction sand rose from 350,000 VND/m³ to about 440,000 VND/m³, while steel and many finishing materials such as paint, wood, and plastic increased by an additional 5 – 15% depending on the type.
On the manufacturing side, Mr. Pham Cong Thao, Deputy General Director of Vietnam Steel Corporation, said that steel production costs have increased by about 50,000 – 100,000 VND/ton due to rising FO oil and LPG prices, while transportation costs have increased by about 10 – 20%. For the cement industry, Mr. Bui Nguyen Quynh, Deputy General Director of Ha Tien Cement, said that coal prices have increased by 7 – 10%, and gypsum and other raw materials have increased by 15 – 20%. Many cement companies have adjusted selling prices up by about 100,000 VND/ton, while Vietnam Cement Industry Corporation has adjusted prices up by about 60,000 – 70,000 VND/ton.
Project estimates increase from 1.91% to 8.09%
The increase in material and fuel prices has directly impacted construction investment costs. It is estimated that construction estimates for projects have increased from 1.91% to 8.09% compared to February 2026, with transportation projects being the most affected, with an increase of 8.09%. For 44 key projects with a total investment of about 569,000 billion VND, the remaining unexecuted value is about 267,000 billion VND; key transportation projects alone could see costs overrun by about 42,300 billion VND.
Fuel supply has also become a challenge for contractors. At the Phu Quoc International Airport expansion project, contractor ACC, which is constructing runway No. 2 and the aircraft apron, needs about 10,000 liters of diesel per day for 160 – 180 pieces of equipment, but since the beginning of March, it has only been supplied with 2,000 – 3,000 liters/day, while the price of diesel has increased from 19,000 to 36,000 VND/liter. The situation of having to collect fuel from many gas stations has also appeared at the Ho Chi Minh City – Long Thanh – Dau Giay expressway expansion project.
Market stabilization solutions
According to Ms. Ma Thi Luan, Deputy Chief of the Office of the Ministry of Construction, the Ministry has strengthened monitoring of market developments, ensuring supply-demand balance, especially for materials serving national key projects, and in the second quarter of 2026, will continue to coordinate with localities to timely grasp price and supply fluctuations. The Ministry requests localities to announce and update construction material prices close to market rates, strictly control the business of gasoline, oil, and construction materials, and prevent hoarding, speculation, and price gouging.
For investors and project management boards, the Ministry of Construction requires strict control of construction investment costs, proactive assessment of the impact of price fluctuations to effectively use contingency costs, and review of contracts, especially lump-sum and fixed-unit-price contracts, to coordinate with contractors to resolve obstacles in accordance with regulations. Investors and contractors also need to proactively assess material needs to ensure supply for continuous construction.
Source: Lao Dong Newspaper, Aviation Magazine.