The Dinh Vu – Cat Hai Economic Zone, with the Nam Dinh Vu Industrial Park as its core, has been asserting its position as one of the key industrial and logistics hubs in the North. This development has led to a high demand for modern factory infrastructure, especially for highly flexible ready-built factories for lease.
Recognizing this demand, Hai Long Steel Structure is currently executing the steel structure installation for the “Factory for lease and auxiliary items” project for the investor, Dumei Vietnam Co., Ltd. The project is a testament to Hai Long's capability in providing effective construction solutions that meet strict standards for schedule and quality.
Project Overview
- Project: Factory for lease and auxiliary items Dumei Vietnam
- Location: Lot CN 5.1B, Nam Dinh Vu Industrial Park, Hai Phong
- Scope of work: Steel structure installation
- Volume: Over 1,200 tons
- Schedule target: 70 days
To meet this schedule, our workflow is organized as follows:
- At the factory: Production lines operate continuously to fabricate components according to the plan. Quality control at the source ensures that products meet the highest technical standards upon dispatch.
- At the construction site: The installation team and equipment are reasonably arranged, ready to receive and install components as soon as they are transported to the site.
The seamless coordination between these two locations is the key factor that helps us control and accelerate the overall project schedule, while ensuring quality and safety throughout the construction process.
Some images at the project site