The project has a total land area of 40,000 m2, built with the following items: 02 factory buildings with a total floor area of 22,740 m2; office building, canteen, rest area, and food storage with a total floor area of 3,965 m2; auxiliary items with a total floor area of 1,173 m2. The expected implementation time is 7 months.

40,000 m2

Land area

26,776 m2

Construction area

02

Factory building

Projectschedule

  • Start
    18/01/2024
  • Finish
    21/08/2024

Projectdetails

  • Schedule update

  • Schedule update

  • Schedule update

  • Schedule update

  • Schedule update

  • 95% of foundations completed, columns and walls under construction

  • Schedule update

  • Schedule update

  • Schedule update

  • Schedule update

  • Groundbreaking ceremony