The Snowcoast project is a significant, large-scale project, highly regarded for its investment level and technical requirements. The project has a total area of 65,000m², of which the construction land area is 38,000m², the green space area is 18,500m², and the total floor area of the project is 47,000m². The total investment is up to 595 billion VND (equivalent to 25 million USD). Beyond construction, Snowcoast also focuses on environmental protection. The project has set criteria to achieve the LEED ZERO green certification, ensuring that the construction process does not negatively impact the surrounding environment.
Commencing construction in August 2023, after nearly 2 months of work, the project has its first progress reports, specifically:
– Piling work: Approximately 85% of the work volume completed
– Main factory: Foundation work is underway
– Office building: Foundation work is underway
– Canteen, parking lot, warehouse: Foundation work is underway
– Fence items: 70% of the work volume completed.
An overview of the project progress shows that the Hai Long Construction team is maintaining the schedule as required by the investor. The quality of the work is also strictly ensured, guaranteeing that the project will meet the high standards of quality and aesthetics set by the Snowcoast project.
Although construction is taking place during the approaching rainy and stormy season on weak soil, the determination and creativity of the team at Hai Long Construction have been clearly demonstrated through finding the best solutions, with many management and supervision measures implemented systematically. The Procurement Department and subcontractors are also accelerating their work. We are committed to completing the project successfully, ensuring it meets the committed schedule.
Some images updating the construction progress of the Snowcoast Vietnam project