The TSMT Vietnam Factory project, with Hai Long Construction as the general contractor, is progressing very favorably and is ahead of schedule. According to the plan, the project will be handed over to the investor by the end of 2023. With high determination from the Project Management Board, Hai Long Construction is making efforts to accelerate progress to hand over the project 15 days ahead of the contract.
Hai Long Construction has focused all resources and determination on accelerating the project handover. With the unity of over 300 workers and engineers working directly on-site every day, the project has completed many important parts.
The project has a construction area of 17,480m2, located in Thai Ha Industrial Park – Ha Nam. As of October 2023, the project is in the finishing stage of Fire Protection and M&E (Mechanical & Electrical) systems. Specifically:
- The project has completed the masonry work for the office building and factory building.
- The parking garage has been 95% completed.
- Auxiliary items: SPL building, waste storage, electrical building, guard house, and pump house have been basically completed.
- Infrastructure: Completed storm water drainage, sewage, and low-voltage systems... Preparing for internal road construction.
- Regarding progress, the project is meeting the investor's required schedule.
- Regarding quality, the project is also being ensured according to technical standards.
The TSMT Vietnam Factory project is not only a construction project that is ahead of schedule and ensures quality, but also a symbol of the relentless spirit and determination to overcome all challenges of Hai Long Construction. The achievements attained demonstrate the clear vision of the management team and workers on-site.
Some images updating the construction progress of the TSMT Vietnam project