UPDATE ON CONSTRUCTION PROGRESS OF NAM DINH VU GNP PROJECT FEBRUARY 02

GNP Nam Dinh Vu project officially started construction on September 27, 09 with the participation of representatives of Hai Long Construction and Installation general contractor and partners to create the project.

Construction image of GNP Nam Dinh Vu Industrial Center project

GNP Nam Dinh Vu Industrial Center has a total area of ​​17 hectares, construction area of ​​more than 100.000m², providing industrial infrastructure including 6 blocks of ready-built factories with flexible area from 2.500 m, ready-built warehouses from 5.000m² designed to suit the diverse needs of businesses. With a total investment of about 38,5 million USD, the project is expected to come into operation in July 7.

Construction image of GNP Nam Dinh Vu Industrial Center project
Construction image of GNP Nam Dinh Vu Industrial Center project
Construction image of GNP Nam Dinh Vu Industrial Center project

Up to now, the items that have been and are under construction in February 02 include:

  • Areas X5, X6 have completed the corrugated iron roof, the foundation, are installing door equipment and finishing the outside office.
  • The warehouse area has completed the steel structure installation and is ready for corrugated iron roofing.
  • Area X1 has completed the steel structure and is roofed with corrugated iron.

Estimate about 41% of the project volume, ensuring the implementation progress as committed with the investor Gaw NP Industrial.

As a pioneer with more than 23 years of experience in the field of implementing large projects for potential and large-scale international partners, Hai Long Construction and Construction projects always focus on ensuring safety, quality, construction progress, reasonable cost.

Image of safety training at the beginning of the hour at the construction site

Specifically, at the GNP Nam Dinh Vu project, Hai Long Construction and Construction emphasizes construction safety at the construction site along with the quality of the work. In order for the implementation of occupational safety to be regular and continuous, training sessions at the beginning of the hour are held every day to raise workers' awareness of safety as well as tighten regulations on safety before work. working session. In addition, the Company also regularly encourages employees' morale with gifts for individuals who ensure safety and successfully complete tasks in construction.

Hai Long Construction Joint Stock Company is committed to focusing all resources, preparing the best staff, completing the project on schedule, ensuring quality, and handing over the project on time as agreed with the owner. private.

Related news
CONFERENCE OF May 05
09-05 2023

CONFERENCE OF May 05

On May 05, 05, Hai Long Construction Joint Stock Company successfully held a briefing session